Mangaluru: A delay in securing permission to lay a major water pipeline along the proposed Mani-Mysuru highway alignment has held up work on certain stretches of the Rs 780-crore multi-village drinking water project in Dakshina Kannada. The project, being implemented under the Jal Jeevan Mission, has achieved around 70% progress.
The Rural Drinking Water and Sanitation Department is targeting December to begin supplying water to Vittal, while Puttur is expected to receive water by March next year.
“We have asked the contractor to complete the Puttur-side work by March,” said Natesh Kumar, assistant executive engineer of the department’s Bantwal division.
The project involves drawing water from the Netravathi River at Shamboor in Bantwal taluk and supplying it to Bantwal, Puttur, Kadaba and Sullia taluks. Its coverage extends to 57 gram panchayats, 79 villages and 739 habitations, catering to an estimated population of 3.5 lakh by 2055.
A jackwell and a water treatment plant with a capacity of 26.4 million litres per day (MLD) are being constructed at Shamboor. The treated water will be distributed through an extensive pipeline network supported by storage facilities and pumping stations.
The scheme envisages a daily supply of 55 litres per capita to rural households and 135 litres per capita in urban areas.
The infrastructure includes 20 zonal balancing tanks, an overhead tank, five intermediate sumps, 17 lifting stations and 17 low-level sumps. The treatment plant will also have a 3.5-lakh-litre wash-water tank.
To ensure uninterrupted power supply to the facility, a dedicated 24-hour express feeder line is being provided from the Mescom substation at Kaladka.
The pipeline network comprises 180.2 km of mild steel pipes, 7.6 km of ductile iron pipes and 1,275.6 km of high-density polyethylene (HDPE) distribution pipelines.
However, a crucial section of the pipeline intended to carry water towards Puttur, Sullia and Kadaba is awaiting clearance from the authorities concerned.
Jagadish, assistant engineer in the department’s Bantwal sub-division, said the alignment of the proposed four-laning of the Mani-Mysuru highway had not yet been finalised, preventing the department from obtaining permission to lay the pipeline along the affected stretch.
“We expect the approvals to come by the end of this month. Until then, we do not have permission to lay the pipeline along that stretch,” he said.
He added that the pipeline work could be completed within one and a half to two months after the necessary clearance is received.